Project Dashboard
Total Budget
$1,250,000
Spent
$875,000 (70%)
Project Progress
65%
Completion
45 days remaining
Materials Cost
$520,000
Budget
$600,000 (87%)
Labor Cost
$355,000
Budget
$450,000 (79%)
Cost Breakdown
Budget vs Actual
Recent Expenses
Project Timeline
June 1, 2023
Site Preparation Completed
All site clearing and preparation work finished on schedule
June 10, 2023
Foundation Work Completed
Concrete pouring and foundation work finished
June 15, 2023 - Current
Framing in Progress
Structural framing 65% complete
July 5, 2023 - Upcoming
Plumbing & Electrical
Scheduled to begin after framing completion
Cost Categories
Materials
$520,000 / $600,000
Labor
$355,000 / $450,000
Equipment
$78,500 / $100,000
Permits
$15,000 / $20,000
Insurance
$12,500 / $15,000
Other
$8,000 / $10,000